This article aims to present method of calculating dates and slack time in PDM diagrams with different types of relationships between tasks. Algorithms that have been worked out by the Author as well as enclosed computational example enable to analyze a process of determining these values. Knowledge of adopted algorithms facilitates accurate interpretation of calculation outcomes and improved construction of relationship networks for users of computer programmes. These two crafts are ultimately fundamental for planning and realization management of engineering objects.