How to calculate dates and slack time in PDM diagram with different relationship types between tasks
Języki publikacji
PL
Abstrakty
EN
This article aims to present method of calculating dates and slack time in PDM diagrams with different types of relationships between tasks. Algorithms that have been worked out by the Author as well as enclosed computational example enable to analyze a process of determining these values. Knowledge of adopted algorithms facilitates accurate interpretation of calculation outcomes and improved construction of relationship networks for users of computer programmes. These two crafts are ultimately fundamental for planning and realization management of engineering objects.
Szkoła Główna Gospodarstwa Wiejskiego, ul.Nowoursynowska 159, 02-776 Warszawa
Bibliografia
KORMAN R., DANIELS S.H. 2003: Critics Can’t Find the Logic in Many of Today’s CPM Schedules. ENR: Engineering News-Record 5, 26 250, 20.
MARCINKOWSKI R. 2008: Teoretyczne podstawy harmonogramowania realizacji zadań budowlanych. Problemy przygotowania i realizacji inwestycji budowlanych. Warsztaty dla inżynierów budownictwa, Puławy 22–24 października 2008 r., Warszawa.
MURRAY B.W. 2007: Faster Construction Projects With CPM Scheduling. McGraw-Hill Professional Publishing, New York.
POŁOŃSKI M. 2001: Harmonogramy sieciowe w robotach inżynierskich. Wydawnictwo SGGW, Warszawa.
POŁOŃSKI M. 2008: Stosowanie rozszerzonych typów relacji w harmonogramach przedsięwzięć budowlanych. Problemy przygotowania i realizacji inwestycji budowlanych. Warsztaty dla inżynierów budownictwa, Puławy 22–24 października 2008 r., Warszawa.